PLANS to build a gas-fired power plant on the north-western edge of Verwood have been refused.
Abingdon-based Conrad Energy said its 5MW facility would have provided a back-up energy supply for the equivalent of 3,000 homes.
But Dorset Council planners said it was “inappropriate” for its proposed green belt location and rejected the scheme on Friday.
Conrad Energy, which has overseen a number of similar projects across the country in recent years, said smaller power stations were required to support the national electricity supply.
It said its proposed new facility at The Old Brickyard off Station Road would provide boosts to the local network “at short notice”.
“The proposed flexible gas-fired power plant is an essential facility in the provision of a secure and sustainable energy supply,” a statement submitted on its behalf by planning consultancy Lichfields said.
“This will be most commonly required at times when renewable energy sources fail to generate sufficient electricity or, alternatively, during short periods of exceptional demand for energy.
“Flexible power plans can only be located where easy access can be achieved to gas supply and electricity substations. As such, the number of locations they can be sited is limited.”
Concerns had been raised about the addition of new non-renewable electricity production in the country, with the scheme opposed by East Dorset Environment Partnership and East Dorset Friends of the Earth.
Objections were also lodged by Verwood Town Council Dorset Campaign to Protect Rural England.
The application was refused by Dorset Council planning officer Gareth Kitching who said the benefits of the power station did not outweigh the protection of the green belt.
“It is considered that the proposal, given its siting and scale, would diminish the open character of this green belt location and add visual clutter within the landscape,” his report says.
“Very special circumstances outweighing the harm by reason of inappropriateness have not been demonstrated in this case.”
Speaking following the decision, Conrad Energy development manager John Colombi said: “We are disappointed with officers’ decision to refuse our application, before it had a chance to be considered by [councillors].
“Our project would have been one of many standby power generators located around the country which are a vital component of the growing renewable energy infrastructure to ensure security of supply and avoid power cuts, as experienced across the country just last week.
“As recognised by both the Government and the National Grid, local standby generation is required to meet requirements for peak demand, and unplanned events to ensure supplies are maintained to customers.”
Mr Colombi said the company would look in-depth at the reasons for refusal before deciding its next steps.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel