The following roadworks are being carried out within the BCP Council area by the council and various utility companies over the next few days:

1. Adastral Road (Poole) – junction with Learoyd Road

Temporary traffic signals on 27 July until 10 August during Cityfibre’s new installation works.

2. Adastral Road (Poole) – junction with Warburton Road

Temporary traffic signals on 2 August until 13 August during Cityfibre’s new installation works.

3. Benmoor Road (Poole) – entire road

Temporary road closure until 20 August during BCP Council’s highway improvement works.

4. Bennion Road – outside 10

Temporary road closure on 2 August until 20 August during new sewer connection works. Signed diversion route in operation.

5. Blandford Road (Poole) – junction with Rigler Road to Tuckers Lane

Temporary (one-way) road closure on 2 July until 20 August during SSE’s maintenance works. Signed diversion route in operation.

6. Burton Road (Christchurch) – junction with Everest Road to Normandy Drive

Temporary (rolling) traffic signals on 2 August until 13 August during Cityfibre’s new installation works.

7. Castle Lane West – junction with Muscliffe Lane

Temporary (night-time) carriageway restrictions on 4 August until 12 August during Vodafone Group’s new installation works.

8. Charminster Road – junction with East Way

Temporary traffic signals on 2 August until 13 August during BCP Council’s highway improvement works.

9. Columbia Road – junction with Hendford Road to Redhill Avenue

Temporary (rolling) traffic signals on 10 July until 18 August during Vodafone Group’s new installation works.

10. Columbia Road – outside 239

Temporary traffic signals on 10 August during BT’s maintenance works.

11. Commercial Road (Poole) – junction with Sandbanks Road to North Road

Temporary carriageway restrictions on 2 August until 13 August during BCP Council’s highway improvement works.

12. Denmark Lane (Poole) – junction with Denmark Road

Temporary road closure on 16 July until 17 September during storm drain connection works. Signed diversion route in operation.

13. Fulwood Avenue – junction with Greystoke Avenue

Temporary traffic signals on 9 August until 13 August during Wessex Water’s maintenance works.

14. Goliath Road (Poole) – junction with Samson Road to David Way

Temporary road closure on 23 June until 17 August during SSE’s maintenance works. Signed diversion route in operation.

15. Harewood Avenue – junction with Littledown Avenue to College Drive

Temporary road closure on 26 July until 10 September during BCP Council’s highway improvement works. Signed diversion route in operation.

16. Holloway Avenue – junction with Anstey Road

Temporary traffic signals on 9 August until 13 August during BT’s maintenance works.

17. Jubilee Road (Poole) – opposite car park

Temporary traffic signals on 10 August until 19 August during SSE’s maintenance works.

18. Kitchener Crescent (Poole) – outside 82

Temporary road closure on 26 July until 9 August during new sewer connection works. Signed diversion route in operation.

19. North Road (Poole) – junction with Commercial Road

Temporary traffic signals on 2 August until 13 August during BCP Council’s highway improvement works.

20. Poole Road – County Gates Gyratory

Temporary carriageway restrictions on 5 August until 11 August during SSE’s maintenance works.

21. Portfield Road (Christchurch) – outside 11

Temporary road closure on 9 August until 13 August during new sewer connection works. Signed diversion route in operation.

22. Prince of Wales Road – junction with Branksome Wood Road to Surrey Road

Temporary (night-time) road closure on 9 August until 12 August during Wessex Water’s maintenance works. Signed diversion route in operation.