The following roadworks are being carried out within the BCP Council area by the council and various utility companies this week:

1. Alder Road (Poole) – outside 329

Temporary traffic signals on 30 July until 19 August during SGN works to locate and repair a leak.

2. Ashley Road – junction Holdenhurst Road to railway bridge

Temporary road closure on 22 July until 29 August during BCP design and improvement works. Signed diversion route in operation.

3. Barnes Road – junction with Howeth Road

Temporary traffic signals on 12 August until 16 August during SSEPD works for a new connection.

4. Benellen Gardens – junction with Benellen Avenue

Temporary road closure on 2 August until 30 August during BCP design and improvement works. Signed diversion route in operation.

5. Bingham Avenue (Poole) – junction with Lilliput Road

Temporary road closure on 22 July until 21 August during SGN installation and maintenance works. Signed diversion route in operation.

6. Bourne Valley Road (Poole) – jct Yarmouth Rd to o/s Branksome Business Park

Temporary traffic signals on 12 August until 23 August during CityFibre installation works.

7. Braidley Road – outside 15

Temporary road closure on 18 July until 6 September during Wessex Water works to repair a collapsed sewer. Signed diversion route in operation.

8. Broadway Lane – junction Careys Road to outside 86

Temporary road closure on 22 July until 10 September during SGN installation and maintenance works. Signed diversion route in operation.

9. Brudenell Avenue (Poole) – junction with Shore Road

Various carriageway restrictions (including a small road closure) on 1 April until 30 August during SGN installation and maintenance works. Signed diversion route in operation.

10. Canford Cliffs Avenue (Poole) – outside 7

Temporary road closure on 29 July until 12 August during BCP works to make a new connection to a sewer.

11. Cavendish Road – outside 55

Temporary traffic signals on 13 August until 20 August during SSEPD works for a new connection.

12. Christchurch Road – Boscombe Spa Road to Knyveton Road

Temporary one way road closure (Eastbound) plus other carriageway restrictions including road closures on Boscombe Spa Road, Knole Road, Knyveton Road and Manor Road, on 2 August until 27 September during Wessex Water works to make an emergency repair for a collapsed sewer. Signed diversion route in operation.

13. Compton Avenue (Poole) – junction with Lilliput Road

Temporary traffic signals on 22 July until 21 August during SGN installation works.

14. Constitution Hill Road (Poole) – jct Ringwood Rd to jct Constitution Hill Gardens

Temporary traffic signals on 22 July until 11 October during SGN installation works.

15. Danecourt Road (Poole) – junction with Ringwood Road to jct Fernside Avenue

Temporary carriageway restrictions including a road closure, on 22 July until 1 September during SGN installation works. Signed diversion route in operation.

16. Durley Road – whole road

Temporary road closure on 22 July until 30 August during BCP junction remodelling works. Signed diversion route in operation.

17. Hurst Hill (Poole) – whole road from Lilliput Road

Temporary traffic signals on 31 July until 27 August during SGN installation works.

18. Lagado Close (Poole) – whole road from junction with Lilliput Road

Temporary traffic signals on 22 July until 13 August during SGN installation works.

19. Lake Drive (Poole) – outside 7

Temporary traffic signals on 8 August until 12 August during Wessex Water works to repair a leaking pipe.

20. Langside Avenue (Poole) – junction with Alder Road

Temporary road closure on 30 July until 19 August during SGN emergency repair and maintenance works. Signed diversion route in operation.

21. Leicester Road (Poole) – outside 6 to 14

Temporary traffic signals on 12 August until 14 August during Wessex Water works to clean and survey the sewers.

22. Leven Avenue – junction Walsford Road and Benellen Avenue

Temporary road closure on 31 July until 30 August during BCP works to improve crossing and cycle facilities. Signed diversion route in operation.

23. Lilliput Road (Poole) – junction Bingham Avenue to jct Dean Swift Crescent

Temporary traffic signals on 22 July until 3 September during SGN installation works.

24. Magna Road (Poole) – outside 122 to junction with Hainault Drive

Temporary traffic signals on 12 August until 6 September during SGN installation works.

25. Normandy Way (Poole) – link road between Lake Drive and Normandy Way

Temporary road closure on 15 April until 6 September during SGN installation and maintenance works. Signed diversion route in operation.

26. Oakley Lane (Poole) – junction with Oakley Straight to jct with Harrier Drive

Temporary road closure on 25 July until 9 September during BCP works to install a new pedestrian crossing and install new kerbs. Signed diversion route in operation.

27. Parkwood Road – junction with Christchurch Road - junction with Darracott Road

Temporary road closure on 8 July until 13 September during SGN installation works. Signed diversion route in operation.

28. Queens Road – junction Surrey Road

Temporary road closure on 5 August until 30 August during SGN installation and maintenance works. Signed diversion route in operation.

29. Ringwood Road (Poole) – junction Fernside Road to junction with Hunt Road

Temporary traffic signals on 22 July until 1 September during SGN works to replace a new gas main.

30. Roumelia Lane - junction Hawkwood Road to junction Adeline Road

Temporary road closure on 6 August until 12 August during SSEPD works to locate a repair a fault. Signed diversion route in operation.

31. Shillingstone Drive – junction Broadway Lane to junction Stratton Road

Temporary road closure on 22 July until 10 September during SGN installation and maintenance works. Signed diversion route in operation.

32. Somerville Road – junction Durley Chine Road to jct Durley Road

Temporary road closure on 22 July until 30 August during BCP works to install a cycle lane and to turn the road into a ‘school street’. Signed diversion route in operation.

33. South Park Road (Poole) – junction with Alder Road

Temporary road closure on 30 July until 19 August during SGN emergency repair and maintenance works. Signed diversion route in operation.

34. Surrey Road - junction with Queens Road to jct Prince Of Wales Road

Temporary carriageway restrictions, including road closures on 3 July until 26 October during SGN works to replace a new gas main. Signed diversion route in operation.

35. Twin Sails Bridge (Poole) – jct with West Quay Road to jct with Blandford Road

Temporary road closure on 17 May until 16 August during BCP ongoing essential maintenance. Signed diversion route in operation.

36. Upper Road (Poole) – junction Lawson Road to junction Brixey Road

Temporary road closure on 26 July until 30 August during SGN installation and maintenance works. Signed diversion route in operation.

37. Uppleby Road (Poole) – junction Ashley Road to junction Upper Road

Temporary road closure on 26 July until 27 September during SGN installation and maintenance works. Signed diversion route in operation.

38. Wallace Road (Poole) – outside 20

Temporary road closure on 14 August during BT maintenance works including works to replace a damaged pole.

39. Western Road (Poole) – outside Solar Court

Temporary traffic signals on 12 August until 30 August during SGN installation works.

40. Wimborne Road – outside 41 to outside 37

Temporary (night-time) carriageway restrictions on 12 August until 23 August during ESP Electricity works for a new supply.

41. Yarmouth Road (Poole) – jct with Wroxham Road to Bourne Valley Road

Temporary traffic signals on 12 August until 23 August during CityFibre installation works.